Variations after signing
A signed proposal is never redrafted. When the site inspection, the customer or the stock changes the job, you make a variation: a new proposal, linked to the contract, that both of you sign before installation.
A signed proposal’s customer card in Proposals (click its row): More actions → Change → Variation. Only an owner or back office sees it.
When the customer signs again
Any change to what the customer signed, its design, system, price or performance estimate, is a variation. The proposal they signed says so: any change to the design or the estimate is put in writing for both of you to sign before installation. Common reasons are a roof or switchboard the inspection found different, a battery swapped for one in stock, or an extra the site needs. A variation is for the same customer: for someone else, start a new proposal.
Make a variation
- Click the signed job’s row in Proposals. On its customer card, press More actions → Change → Variation. Make a proposal fills with the signed job as a new proposal for the same customer, with its own link.
- Change what changed, and press Generate draft →.
- Send it, as you’d send any proposal. See sending.
- The customer signs it. Its row then reads Signed · countersign, and it’s in Needs you.
- An owner or back office clicks its row and presses Countersign, the customer card’s Next step.
At the same address, a variation uses no prepaid proposal.
While it’s open
- The signed contract stands as it is, billed and counted as before, and its page stays whole. The variation waiting for your countersignature isn’t counted as a second sale: it stays out of the Dashboard’s pipeline and signed counts.
- The job can’t be marked installed until the variation is signed by both of you, or voided before the customer signs it.
- The variation’s page opens with “This is a variation of your signed contract”, the reference and the day it was signed, and says it changes that contract only once both of you have signed it. It says what changes in the price, and that anything already paid under the contract counts towards the payments; it asks for no new deposit.
- The variation carries the signed job’s network application and meter numbers, its site photos, its battery site plan and, on a VEU job, its evidence photos and VEU record. Add VEU photos and record the work on the variation; the original refuses them while the variation is open.
Once both have signed
The original is marked replaced: it reads Replaced in Proposals, and its page tells the customer it has been replaced by a newer version, with a link to it. The variation is now the job in Jobs and Finance, keeping the install booking (or the hold) of the contract it replaced. In Finance, what was paid on the original carries over: the variation, marked “variation of” the original’s reference, bills its own price less what was paid. A payment already invoiced on the original carries over too, so only the difference is left to invoice (“… to invoice (the difference)”). Nothing more is billed on the original. The variation keeps the day the job was first signed, so the Dashboard counts it as the same sale. Not going ahead, before the customer signs it? Void the variation, and the original carries on. If a variation was linked to the wrong job, the owner can press Unlink at the foot of the replaced one’s More actions. See a replaced contract.
Both of you signing a variation is part of the NETCC code; the rule itself is the code’s, at newenergytech.org.au.
Next: The job sheet and battery site plan